Our client was lacking in available laboratory space to accommodate the equipment needed for pipeline biologics production. They required the design and construction of a MABs analytical testing laboratory as an extension to the existing multi-purpose lab facility.

15

air changes per hour

21C +/-3

 temperature control

65%

humidity levels

Client's Requirement

The client required a pharmaceutically clean laboratory with a 15 air-change per hour target regime for class 1 operation. Air filtration needed to suit pharmaceutically clean specifications and the HVAC system designed to cope with the high winds experienced on site. The facility also required state-of-the-art laboratory equipment, unique to the testing protocols of the client, and this equipment needed various services, such as gas and extraction to operate in an efficient and safe manner.

Our Solution

The main challenge was integrating existing services with the new facility, without compromising ongoing operational activity. This required close coordination between ourselves and the client, so daily meetings were organised between the project teams to ensure any construction work had minimal impact.

Our solution included the erection of a new steel framed building, resting on a pad foundation and raft slab base. With an insulated white metal cladding system, the shell was connected to the main facility via an existing doorway. We also built an emergency exit doorway which served as an access route throughout the construction phase; this maintained optimal segregation of construction works from the operational facility.

We provided a new recirculating packaged air handling unit and DX refrigeration system, so heating and cooling infrastructure would not be reliant on the existing facility, and were able to achieve temperature control of 21 C+/- 3 degrees and maximum humidity levels of 65%. We also installed a dedicated BAS control system to perform ventilation system controls, as well as monitor room and equipment conditions. LED lighting and emergency lighting was installed throughout, providing 500 LUX average in laboratory environments.

Client Benefits

Single point of accountability
Providing detailed design, architectural, construction, procurement, installation, mechanical & electrical services, commissioning and validation to offer seamless engineering solutions to the challenges facing our client.

Positive growth with minimal disruption
The additional space gained from the new laboratory will increase productivity, without the need for any facility shut-down during the construction phase.

Quality and excellence
The high quality standard of the facility means our client have a showpiece laboratory which can be cleaned, operated and maintained according to current EU and US good quality control laboratory practice requirements.

Greener laboratory solutions
The new building services, plant and equipment are energy efficient, improving sustainability whilst also reducing running costs for our client.

Latest case studies

0 1 2 3

Block "Nos Engagements"

Our Commitments

De-risk Project Development

Accompanying you through the whole project development from concept stage to handover

 

Technical Expertise

Leveraging our engineering design and construction technique to accelerate and realise the vision of our clients 

 

Compliance Strategies Within Regulated Sectors

Ensuring MHRA and FDA regulations are met as required

 

 

Lean Operation

Ensuring greater long-term operational efficiency and productivity

Latest news

Find all the topics that make Bouygues Energies & Services news: projects, innovations, public and client events, partnerships, press releases ...

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267